Detailed Outline of Training - Single Ply Thermoset Roofing |
Single Ply Thermoset Roofing
| Time | Ref. Manual | |
| 1) General Overview
a. What is single ply (EPDM) roofing i. Roof system types (looselaid, mech. fast., full adh.) ii. Identify materials b. Major steps for installation |
0.5 hr | 6, 6b
(415) (417-420) (416, 426, 433-436) (420-427) |
| 2) Identify Tools and Equipment
a. Protective equipment, safety precautions b. Hand tools & safe practices c. Hoists |
3 hr | 6, 2a, 1a
(139, 4, 5) (416-418), (139-157) (191-205) |
| 3) Prepare the Work Site
a. Moving equipment and supplies i. Handling materials and load trucks ii. Loading the roof |
2 hr | 1a
(6-7) (38-44) (44-45) |
| 4) Preparing the Deck
a. Deck type (wood, steel, etc) b. Cleaning deck - removing ice, snow, water (hazards) – removing debris |
4 hr | 6b, 3a, 3b
(229-233), (420) (233-237, 286-291) |
| 5) Apply EPDM Membrane
a. Identify insulation materials i. Draw and place insulation ii. Protect (cover insulation) iii. Gather & dispose of scrap b. Apply membrane materials - Mechanically fastened, full. Adhered, Looselaid c. Seams |
5 hr | 6b
(272-279, 320) (44-45)
(420-427)
|
| 6) Edges, Flashings & Joints | (431-438) | |
| 7) EPDM Application Tips - Do’s and Don’ts | (450-452) | |
| 8) Project Close Down
a. Remove materials from roof i Load materials on trucks or stockpile b. Remove debris, scrap c. Remove equipment d. Load onto trucks e. Clean stains, spills, etc. f. Remove protective equipment (ladders, etc.) |
1 hr | 1a, 1e
(35-45, 1-4)
(101) |
| Total 15.5 hr |