Detailed Outline of Training - Single Ply Thermoplastic Roofing |
Single Ply Thermoplastic Roofing
| Time | Ref. Manual | |
| 1) General Overview
a. What is single ply (TP) roofing i. Roof system types (looselaid, mech. fast., full adh.) ii. Identify materials b. Major steps for installation |
0.5 hr | 6, 6a
(383) (387-389) (385-386) (357-358) |
| 2) Identify Tools and Equipment
a. Protective equipment, safety precautions b. Hand tools & safe practices c. Hoists |
3 hr | 6, 2a, 1a
(139, 4, 5) (386, 139-157) (191-205) |
| 3) Prepare the Work Site
a. Moving equipment and supplies i. Handling materials and load trucks ii. Loading the roof |
2 hr | 1a
(6-7) (38-44) (44-45) |
| 4) Preparing the Deck
a. Deck type (wood, steel, etc) b. Cleaning deck - removing ice, snow, water (hazards) – removing debris |
4 hr | 5, 3a, 3b
(229-233), (389) (233-237, 286-291) |
| 5) Apply Thermoplastic Membrane
a. Identify insulation materials i. Draw and place insulation ii. Protect (cover insulation) iii. Gather & dispose of scrap b. Apply Membrane materials - Mechanically fastened, full. Adhered, Looselaid c. Seams & welds d. Protected membrane |
5 hr | 6a
(272-279, 320) (44-45)
(390-392)
|
| 6) Edges and Flashings | (395-397) | |
| 7) PVC Application Tips - Do’s and Don’ts | (413-414) | |
| 8) Project Close Down
a. Remove materials from roof - Load materials on trucks or stockpile b. Remove debris, scrap c. Remove equipment d. Load onto trucks e. Clean stains, spills, etc. f. Remove protective equipment (ladders, etc.) |
1 hr | 1a, 1e
(35-45, 1-4)
(101) |
| Total 15.5 hr |